Despite the atrocious weather of late, site activities have continued. so far this week, we have have finished installing the stone pad for the crane. This will now be compaction tested for strength to ensure its suitability for siting the crane.
We have also put up temporary protection towers for the two kiosks inside the site and installed a wireless CCTV unit.