Hello residents!

The excavation work is progressing well and we have managed to excavate approximately 80% of the new tank area.

The access road that we are constructing within the site is 50% complete. This road will allow our delivery vehicles to be able to get to the work area and turn around before leaving the site which will eliminate the need for us to reverse the vehicles out of the site. And it seems the new time slot for deliveries is working well which I am very pleased about. Now that our site set up is complete, I can spread deliveries out during the day. So a little less disruption all round!

The new entrance gates are now up to replace the damaged brick pillars.

I hope our first week on site wasn't to painful for you all, but if you do have any questions please don't be shy, just leave a comment on here or give me a call on my mobile.

Thank you

Barry

0 comments

Please Login in order to comment on this update.

View all Updates

Location

Follow the project

If you would like to be kept up-to-date with all the activity on this project, please register and follow the project here to receive notifications.

Registered Office: Chawston House, Chawston Lane, Chawston, Bedfordshire, MK44 3BH
Registered in England & Wales Number: 1721842   VAT Number: 382 2865 32

Copyright © 2024 Stonbury Limited